Design a bridge

Students find a pinned deck collapses and a big triangle buckles, learn that a member's buckling load falls with its length squared, build a bridge of short triangles that holds 1000 N, then refine it to cost $300 or less and fail only at 1400 N or more.

Structures · Frames and trusses · about 50 minutes · Open the student lesson

Classroom resources

Load these into Waypoints Prepare: choose Load URL and paste the copied address, or download the file and import it. In Prepare, the worksheet's Teacher edition shows the answers; the student copy hides them.

Students will be able to

Timing

Predict and Try 10 min · Worked example 8 min · Vary 12 min · Practise and Make 20 min

Before class

Do Pull or push and Triangles hold their shape first.

The model: a pin-jointed truss; any member pulls up to 2000 N; a member L m long buckles under 8000 ÷ L² N (Euler's buckling falls with length squared; the constant is chosen for the lesson). The load hangs at C only. A Pratt or Howe truss of 13 members ($293) is the cheapest design that meets the Make brief on this grid; teachers may find others.

A spaghetti or straw bridge tested to failure is the natural class follow-up, using the same rules.

Curriculum hooks: Design and Technologies, engineering principles and systems (primary); Science, forces; Maths, powers and inverse proportion.

Running the lesson

  1. Predict: hang a chain between two hands: why does it sag?
  2. Try: ask what made A-G fail when its force was under 2000 N.
  3. Worked example: push on a long straw and a short one.
  4. Make: share costs and failure loads on the board; who was cheapest and still safe?

The hard part (on purpose)

Building takes trial and error, and a design can collapse for a missing member or fail for a long pushed one. Ask which of the two happened.

When students get stuck

What you will seeA question to askThe fix
The bridge collapses.Which joint has members in only one direction?Every joint needs members in two directions.
A long member fails.Is it red (pushed)? Can you make it shorter, or make it pull?Short pushes, long pulls.
It is over budget.Which members carry 0 N?Zero-force members may be removable, but test: some hold a joint in place.

Answers to the checks

  1. just a deck: The bridge is only its deck: A-B, B-C, C-D, D-E, joined by pins. With 1000 N at C, it…
    It collapses. Pins let each joint turn, so a straight row of members folds at C like a chain. Every joint needs members in two directions.
  2. The deck: Press Test it.

    It collapses: the deck folds at its pins.
  3. A big triangle: Build one big triangle: add A-G, G-E and C-G, then B-G and D-G so B and D are held too. Test it.

    It holds its shape, but A-G and G-E, 4.5 m long, buckle under the push.
  4. Why A-G?: Why did A-G fail when no member pulls more than 2000 N?
    It is long and pushed: a long member buckles under a much smaller push
    A 4.5 m member buckles at about 400 N. Long members should pull, or be cut into short ones.
  5. Buckling: On this board, at what push does a 2.83 m member buckle, to the nearest 10 N?
    1000
    8000 ÷ 2.83² = 8000 ÷ 8 = 1000 N.
  6. Shorter: A pushed member is cut in half by bracing it at its middle. How much bigger a push can each half take?
    4 times
    Buckling goes with 1 ÷ length², so half the length takes 2² = 4 times the push.
  7. Vary: a bridge that holds: Build a bridge that holds 1000 N with every member within its limit. Test it.

    A row of short triangles: every joint is held and the long members pull.
  8. Buckling: On this board, at what push does a 4 m member buckle, in newtons?
    500
    8000 ÷ 16 = 500 N.
  9. Safety: A bridge carries 1000 N and fails at 1400 N. What is its safety factor (failure load ÷ working load)?
    1.4
    1400 ÷ 1000 = 1.4.
  10. Cost: A bridge uses 14 members of 2 m and 4 of 2.83 m, at $10 a metre. What does it cost, in dollars, to the nearest dollar?
    393
    28 + 11.32 = 39.32 m, × $10 = $393.
  11. The cheapest safe bridge: Build a bridge that holds 1000 N, costs $300 or less, and gives way only at 1400 N or more. Test it, then load it until it fails.

    A Pratt (or Howe) truss: 13 members, $293, failing at about 1414 N.

Solutions

One possible solution for each task. Other correct programs are fine.

Vary: a bridge that holds

Open task: any program that does what the step asks.

the cheapest safe bridge › The cheapest safe bridge

Open task: any program that does what the step asks.

the cheapest safe bridge › Evaluate

Open task: any program that does what the step asks.

Stretch and support

Stretch: Find a design that fails at 2000 N or more. What does it cost, and is the extra safety worth it?

Support: Give the Pratt truss as a member list to type in, then ask students to remove one member and test.

Exit ticket

A 3 m member on this board is pushed with 1000 N. Will it buckle? Show the sum.

8000 ÷ 3² = 8000 ÷ 9 ≈ 889 N, less than 1000 N, so it buckles.

What each step is for

Where it leads

Next: the Capstone projects, where a lift or drive base meets a real structure.

Real examples: Pratt and Howe trusses (railway bridges), Warren trusses, the Sydney Harbour Bridge arch, roof trusses.